Project Description

Rest & Relax - Heathrow Terminal 5

Project: Rest & Relax
Location: Heathrow, T5
Client: Mace Ltd
Value: £242,222

Job Description

The Business Case was for the provision of space in Terminal 5 Departures for the formation of a new Passenger Lounge. This space was created by the relocation of the Children’s Play area, which in turn meant relocation of the office space taken over by the new Play area.

Method

Meads were involved in several aspects of this project, including; Hoarding, Screeding, Painting, Firestopping, Supply/instal new door & relocate other doors, dismantle and crate up redundant Play Area equipment for future use.

Programme

Work was carried out at night over 16 weeks

Benefits to Client

Meads Construction were able to offer the client the combination of their product knowledge and airport experience. This, together with a multi-skilled workforce and the presence of a management team based at T5 and our own storage facility close by, meant the project could be managed in detail on a daily basis to maximise productivity in the 4 hours available each night.